Part 11 of 11 in the Reforming the Energy Vision series (NY PSC Case 14-M-0101).
Four years into REV, two 2018 filings show where the value conversation had landed. One is a non-wires solicitation for a single overloaded neighborhood, with growth, hours and megawatts spelled out. The other is a utility looking past avoided T&D entirely, to platform revenue from street lights.
West Haverstraw: what a real deferral need looks like
On June 29, 2018, Orange & Rockland filed its request for proposals for a non-wires alternative in West Haverstraw. The problem was specific. Two of the three circuits serving the village share a double-circuit pole line, and "During peak summer loading periods, the remaining area circuit cannot support the entire load." The traditional fix "would include the construction of a new underground circuit from the West Haverstraw substation to the intersection of Route 202 and Route 9W" [F1 p.4].
The cause was growth. In O&R's words: "Increased load growth in the area have eradicated full backup and redundancy capability of local circuits, resulting in some area customers remaining out of power until repairs are completed" [F1 p.8].
And the RFP put numbers on the need [F1 p.8]:
- Megawatts: the "Total Needed Reduction" rises from 4.44 MW in 2019 to 5.83 MW in 2030.
- Hours: "Yearly Hours of Risk" rise from 759 in 2019 to 1,172 in 2030.
- Time of day: "The hours of relief needed in 2018 to 2030 are from 6a.m. to 11p.m."
The three circuits served "4,179 customers" [F1 p.7]. O&R said it would "leverage its existing EE and DR programs to lower the amount of DER that needs to be procured" [F1 p.7], and it pointed bidders to its benefit-cost analysis (BCA) Handbook for how proposals would be valued [F1 p.4].
Set that next to the 2015 record. Con Edison and O&R had said deferral value depends on "Load growth rates and anticipated changes in load curve shapes" [F2 p.21]. West Haverstraw is the template: a growing load, a named asset, a forecast of the shortfall by year, and a window of relief that runs seventeen hours a day. That's the kind of need distribution value is built on.
Smart City: looking for value beyond avoided T&D
Three months earlier, National Grid proposed a demonstration in Schenectady using "approximately 4,275 street lights" as a communications platform [F3 p.3]. The value proposition wasn't avoided wires. It was platform revenue: "If successful, the Company expects to propose new tariff offerings and platform services revenues (“PSRs”) enabling municipal adoption of advanced street lighting and smart-city technologies across National Grid’s New York service territory" [F3 p.4]. National Grid saw scale behind it: "the more than 200,000 street lights that span its service territory could serve as the platform for the widespread adoption of smart-city technology" [F3 p.5].
It's a reminder that Track Two's "earnings from market-facing platform activities" [F4 p.5] were meant to be a second way for utilities to earn, alongside deferral. In a territory without much load growth, deferral opportunities are scarce, and platform revenue was one place to look.
Where the first four years left things
Reading 2014–2018 in order, a few things stand out:
- REV started in a flat-load world. Staff's 2014 report said "The sales base for utilities is relatively flat while peak demand continues to grow" [F5 p.12]. The big early value estimates came from flattening the system peak, not from deferring growth-driven upgrades.
- Distribution value turned out to be local and growth-driven. The utilities said so in 2015 and 2016, and the first distribution plans showed how much of the system had room to spare.
- The rules for counting it got strict. Location-specific marginal costs, functional equivalence, diminishing returns, an end date when the upgrade is built anyway, and hours that match the local peak.
- The earnings rule came first. Brooklyn-Queens showed a utility could earn on not building. Track Two made that general.
- The places where it worked looked like West Haverstraw. A named asset, a growth forecast, a defined shortfall, and a procurement.
That's REV's first four years. The series introduction, Fast Forward, puts them next to today's debates.
Sources
| F# | Filing | Date | Document | Pages cited | Links |
|---|---|---|---|---|---|
| F1 | 14-M-0101, item 1139 | 2018-06-29 | O&R West Haverstraw NWA RFP | p.4, p.7, p.8 | View filing · Original (NY DPS) |
| F2 | 14-M-0101, item 528 | 2015-10-26 | Con Edison and O&R Track Two comments | p.21 | View filing · Original (NY DPS) |
| F3 | 14-M-0101, item 1102 | 2018-03-26 | National Grid Smart City REV demonstration project proposal (Schenectady) | p.3, p.4, p.5 | View filing · Original (NY DPS) |
| F4 | 14-M-0101, item 748 | 2016-05-19 | Track Two Order: Order Adopting a Ratemaking and Utility Revenue Model Policy Framework | p.5 | View filing · Original (NY DPS) |
| F5 | 14-M-0101, item 6 | 2014-04-25 | DPS Staff Report and Proposal, Reforming the Energy Vision | p.12 | View filing · Original (NY DPS) |
Page numbers are physical PDF pages.