REV, Part 11: Load Growth, One Feeder at a Time (2018)

A West Haverstraw non-wires solicitation shows what a real deferral need looks like, while National Grid looks to street lights for platform revenue.

Four years into REV, two 2018 filings show where the value conversation had landed. One is a non-wires solicitation for a single overloaded neighborhood, with growth, hours and megawatts spelled out. The other is a utility looking past avoided T&D entirely, to platform…

Charlie Umberger
Read
Regulatory History

REV, Part 10: Who Captures the Value? Storage Business Models and the LMI Exception (June–August 2017)

A Con Edison battery demonstration split value among four parties, and the Commission clarified when utilities may own DER for low- and moderate-income customers.

By mid-2017, the question in REV was shifting from what is DER worth? to who gets the value? A Con Edison storage demonstration tried to split it between a host customer, a developer, the utility and the wholesale market. Two months later, the Commission clarified when a…

Charlie Umberger
Read
Regulatory History

REV, Part 9: Paying for Performance — The Standby Credit and the Scorecards (December 2016–June 2017)

Two smaller fights over one question: should DER be paid for verified device performance, or for outcomes however they're achieved?

Track Two set the framework for how utilities earn. The fights that followed were about the details of how customers and DER get credited, and how anyone would measure whether REV was delivering. Two filings from this period show the same tension from different sides: should…

Charlie Umberger
Read
Regulatory History

REV, Part 8: Where the Load Was — The First Distribution Plans (June 2016–March 2017)

The first utility distribution plans showed most of the grid had room to spare, and set strict rules for earning deferral value.

On June 30, 2016, New York's utilities filed their first Distributed System Implementation Plans (DSIPs). For the first time, the people valuing DER could see the utilities' own growth forecasts, beneficial locations and benefit-cost handbooks. What they showed, at least in…

Charlie Umberger
Read
Regulatory History

REV, Part 7: Track Two — Getting Paid for Not Building (May 2016)

The Track Two Order let utilities earn money on projects that avoid building, with Brooklyn-Queens as the model.

On May 19, 2016, the Commission issued its Order Adopting a Ratemaking and Utility Revenue Model Policy Framework, the Track Two Order. If Track One decided who would run the platform, Track Two decided how the platform would make money. Its starting premise was that the old…

Charlie Umberger
Read
Regulatory History

REV, Part 6: Planning for Growth — Baldwinsville and the DSIP Guidance (March–April 2016)

National Grid's first open non-wires solicitation, and the Commission's guidance on what every utility distribution plan must show.

By spring 2016, New York had a test for value. What it needed next was information: where the grid was constrained, where load was growing, and where DER could actually defer something. Two filings from March and April show the gap from both ends: one utility's first open…

Charlie Umberger
Read
Regulatory History

REV, Part 5: Counting Value — The Societal Cost Test Wins (January 2016)

New York chose the Societal Cost Test, rejected generic adders, and wrote location-specific distribution value into its benefit-cost rules.

On January 21, 2016, the Commission issued its Order Establishing the Benefit Cost Analysis Framework. It settled which test New York would use to decide whether DER is worth buying, which benefits count, and how to value avoided distribution. Two weeks earlier, a…

Charlie Umberger
Read
Regulatory History

REV, Part 4: The "Value of D" — Staff's 2015 White Papers and the Utilities' Reply (July–October 2015)

Staff proposed valuing DER at LMP plus a 'value of D.' The utilities answered that distribution value depends on where load is growing.

In the summer of 2015, Staff issued two white papers: one on benefit-cost analysis (July 1) and one on ratemaking and utility business models for Track Two (July 28). Together they set out New York's first detailed answer to the question every DER docket asks: what is a…

Charlie Umberger
Read
Regulatory History

REV, Part 3: The Utility Becomes the Platform (February–March 2015)

The Track One Order made utilities the platform for distributed resources, and said those resources deserve pay for the value they provide.

On February 26, 2015, the Commission issued its Track One Order, the "Order Adopting Regulatory Policy Framework and Implementation Plan." It made the distribution utilities the platform for distributed energy resources. It also gave the clearest statement yet of the…

Charlie Umberger
Read
Regulatory History

REV, Part 2: Putting a Price on "System Value" — The Straw Proposal and the First Fights (July–December 2014)

Staff's Straw Proposal put billion-dollar figures on system value and admitted one avoided-cost number per utility wasn't good enough.

The April 2014 Staff report promised to "monetize" system values. Over the rest of 2014, Staff and the parties started arguing about what those values were, who would calculate them, and how much they were worth.

Charlie Umberger
Read
Regulatory History

REV, Part 1: Flat Sales, Rising Peaks — Why New York Decided to Rewire Utility Regulation (April 2014)

In 2014, New York saw flat sales, rising peaks and $30 billion of grid spending ahead, and decided the old utility model couldn't keep up.

On April 25, 2014, the New York Public Service Commission opened Case 14-M-0101, Reforming the Energy Vision. It said it would "comprehensively consider how our regulatory paradigm and retail and wholesale market designs either effectuate or impede progress toward achieving…

Charlie Umberger