NY DPS
Regulatory History

REV, Part 9: Paying for Performance — The Standby Credit and the Scorecards (December 2016–June 2017)

Two smaller fights over one question: should DER be paid for verified device performance, or for outcomes however they're achieved?

Charlie Umberger3 min read

Part 9 of 11 in the Reforming the Energy Vision series (NY PSC Case 14-M-0101).

Track Two set the framework for how utilities earn. The fights that followed were about the details of how customers and distributed energy resources (DER) get credited, and how anyone would measure whether REV was delivering. Two filings from this period show the same tension from different sides: should value be paid for verified performance, or for outcomes however they're achieved?

The standby reliability credit

Track Two "directed the electric utilities to offer a reliability credit to standby customers that maintain a load below their contract demand, regardless of how the customer achieves the lower load level (the as-used demand approach for calculating the reliability credit)" [F1 p.2]. Customers could "exclude up to three outage events per year from the summer period" [F1 p.2].

The Joint Utilities asked the Commission to reconsider. Their argument was a value argument: the as-used method "conflicts with REV’s premise that compensation for DER should reflect payment for performance." They said it "would provide standby customers with unwarranted financial benefits, such as where the weather is cooler than normal in two consecutive summers" [F1 p.3]. And crediting a customer whose generator hadn't proven reliable "could have the effect of bundling reliability and demand response" [F1 p.4].

The Commission said no. It had already found the generator-performance approach inconsistent with REV's goal "of reliably reducing demand on the utility system during peak periods" by any means [F1 p.8]. It conceded the weather point had been "theoretically correct" when first raised, but "The Petition for reconsideration offers no practical methods for normalizing external factors" [F1 p.8]. The utilities' claims, it said, "do not acknowledge that the principles and objectives of REV go beyond a strict adherence to reliability concerns" [F1 pp.7–8]. Its bottom line: "The Track Two Order reasonably balanced REV’s objective of ensuring accurate cost allocation with the goal of removing barriers to DER penetration in order to lower customer bills and improve reliability of the electric grid" [F1 p.9].

Who measures the outcomes?

Track Two also created scorecards for outcomes that weren't ready to drive earnings. In May 2017, Staff proposed "to use individual EAM collaborative meetings and rate cases to develop scorecard metrics." The Clean Energy Organizations Collaborative objected that this "would pose a significant burden on public interest and other stakeholders," and asked Staff to "institute a collaborative process to develop scorecard metrics, as required by the Commission’s Track Two Order" [F2 p.1].

The letter explains why the stakes were higher than a process dispute. "Many of the scorecard metrics are intended to measure key REV and State Energy Plan outcomes and are linked to important potential future EAMs, such as affordability, carbon reduction, DER penetration, and market development" [F2 p.2]. It quoted the order's description of scorecards as tools for cases where "reliable metrics have not yet been developed" [F2 p.2].

The takeaway

These are smaller fights than Track One or Track Two, but they're the same value question at a finer grain. The utilities wanted pay tied to verified device performance; the Commission accepted outcome-based credit with known imprecision (weather) rather than add barriers. Advocates wanted the outcome metrics built in one shared process rather than utility by utility. Both point to how hard it is to pay for value you can't yet measure precisely.


Sources

F# Filing Date Document Pages cited Links
F1 14-M-0101, item 894 2016-12-15 Order Denying Petition for Reconsideration (standby reliability credit) p.2, p.3, p.4, pp.7–8, p.8, p.9 View filing · Original (NY DPS)
F2 14-M-0101, item 998 2017-06-09 Clean Energy Organizations Collaborative letter on scorecard metrics p.1, p.2 View filing · Original (NY DPS)

Page numbers are physical PDF pages.

Case 14-M-0101

Follow the case
About the Author

I have spent the last decade trying to get distributed energy resources on the grid, paid, operated, and integrated into utility operations and business.

Related Insights

Regulatory History

REV, Part 8: Where the Load Was — The First Distribution Plans (June 2016–March 2017)

On June 30, 2016, New York's utilities filed their first Distributed System Implementation Plans (DSIPs). For the first time, the people valuing DER could see the utilities' own growth forecasts, beneficial locations and benefit-cost handbooks. What they showed, at least in…

Regulatory History

REV, Part 10: Who Captures the Value? Storage Business Models and the LMI Exception (June–August 2017)

By mid-2017, the question in REV was shifting from what is DER worth? to who gets the value? A Con Edison storage demonstration tried to split it between a host customer, a developer, the utility and the wholesale market. Two months later, the Commission clarified when a…

Compensation & Rates

Fast Forward: New York Is Still Arguing Over What a Kilowatt Avoids

The rest of this series moves through Case 14-M-0101 one filing at a time and never looks ahead. This post breaks that rule on purpose. Before we go back to 2014, here's where two of REV's biggest value questions stand in late 2026.