Part 2 of 11 in the Reforming the Energy Vision series (NY PSC Case 14-M-0101).
The April 2014 Staff report promised to "monetize" system values. Over the rest of 2014, Staff and the parties started arguing about what those values were, who would calculate them, and how much they were worth.
Developers asked for a price signal by location
Some of the earliest comments went straight to valuation. The Northeast Clean Heat and Power Initiative (NECHPI) told the Commission in July that "A key issue today is that utilities do not understand what it costs them to serve each customer. What is needed is a “value signal” that shows cost by customer and by location" [F1 p.23]. It asked the Commission to pursue "new standardized and transparent valuation methodologies" [F1 p.23].
Staff's August Straw Proposal: big numbers, but "premature" to be precise
Staff's August 22 Straw Proposal, "Developing the REV Market in New York," listed the benefits REV should produce, including "Deferral or avoidance of transmission and distribution (T&D) infrastructure investment." It added that "Some of these benefits are more easily quantified than others, but all should be accounted for" [F2 p.13].
It also gave illustrative numbers, while saying it was "premature to develop precise figures at this time" [F2 p.13]. The headline was about load shape, not load growth: "if the 100 hours of greatest peak demand were flattened, long-term avoided capacity and energy savings would range between $1.2 billion and $1.7 billion per year. Merely increasing the system load factor from 55% to 56% would produce potential gross benefits of $150 million to $219 million per year" [F2 pp.13–14]. Staff's footnote explained that the estimate included "avoided generation capacity, avoided T&D investment, and avoided energy payments including line losses" [F2 p.14].
For distribution deferral specifically, Staff pointed to two live examples. Con Edison's Brooklyn/Queens Demand Management petition and PSEG Long Island's Utility 2.0 plan "illustrate both the potential benefits and the achievability of non-wires alternatives. Consolidated Edison proposes to acquire 52 MW of distributed resources to address overloaded distribution facilities" [F2 p.14].
The admission: one number per utility wasn't good enough
The most consequential sentence in the Straw Proposal may be in a table of benefit-cost inputs. Under "Distribution costs," Staff wrote: "In the past, staff used one system-wide number for each utility for avoidable distribution capacity costs. This is clearly inadequate for the advanced planning and operation envisioned under REV. More detailed estimates of avoidable distribution costs tailored to specific locations, resources, and procurements should be developed for the BCA" [F2 p.52].
Staff tied that to the physical question underneath: "Effectively assessing the benefits of DERs requires accurately assessing the amount of energy, capacity, and other benefits that those resources provide, and, often, when and where they will be provided" [F2 p.51]. And it said the same benefit-cost framework "could be used to arrive at appropriate tariff rates," with that application to be "considered as part of the REV proceeding’s Track Two" [F2 p.53].
The utilities: procure first, price later
The Joint Utilities backed "a phased approach, along the lines envisioned by Staff in the Straw Proposal" [F3 p.34]. On how distributed energy resources (DER) would be bought in the near term, they were specific: "utilities may focus on direct procurement of DER via projects such as Con Edison's Brooklyn-Queens Demand Management program. In time, such an approach could transition to price signals and, ultimately, to functional operating markets" [F3 p.35].
They also supported utility ownership of DER with safeguards, arguing that "Regulated utility ownership of DERs by its nature provides regulators with an added degree of control" [F3 p.33].
DER companies: publish the value, and watch the platform
EnergyHub and Alarm.com quoted the Straw Proposal's own goal that "Customers and energy service providers should have access to system information, to make transparent and readily available the economic value of time- and location-variable usage" [F4 p.5]. They wanted that information in a common format statewide. They also quoted Staff's conclusion that "market power must be addressed in any event" and asked for "a periodic review of the DSP function" [F4 pp.6–7].
December: start building before the rules are final
In December, the Commission urged utilities and third parties to begin demonstration projects even before it ruled on Track One. Data from those projects "will inform regulatory changes, rate design, and the most effective means to integrate DER on a larger scale" [F5 p.1].
Its list of projects already underway included the clearest load-growth example in the state. Con Edison had petitioned "for approval of a non-traditional customer-sided and electric utility-sided demand management program intended to defer major transmission and distribution capital investments that would otherwise be needed to address increased electricity demands in its Brooklyn and Queens service areas" [F5 p.3]. Parties broadly supported demonstrations, though some "raised concerns about the criteria to be applied to such projects and about cost recovery issues" [F5 p.4].
The takeaway
By the end of 2014, the shape of the value debate was set. Staff's big numbers came from flattening the system peak. But the one concrete deferral example on the table, Brooklyn-Queens, came from something else: growing demand against an overloaded local facility. And Staff had already conceded that a single avoided-cost number per utility was "clearly inadequate."
Sources
| F# | Filing | Date | Document | Pages cited | Links |
|---|---|---|---|---|---|
| F1 | 14-M-0101, item 75 | 2014-07-21 | NECHPI comments on Track 1 and Track 2 questions | p.23 | View filing · Original (NY DPS) |
| F2 | 14-M-0101, item 109 | 2014-08-22 | DPS Staff Straw Proposal on Track One Issues | pp.13–14, p.13, p.14, p.51, p.52, p.53 | View filing · Original (NY DPS) |
| F3 | 14-M-0101, item 153 | 2014-09-22 | Joint Utilities comments on the Straw Proposal | p.33, p.34, p.35 | View filing · Original (NY DPS) |
| F4 | 14-M-0101, item 172 | 2014-09-23 | EnergyHub and Alarm.com comments on the Straw Proposal | p.5, pp.6–7 | View filing · Original (NY DPS) |
| F5 | 14-M-0101, item 285 | 2014-12-12 | Memorandum and Resolution on Demonstration Projects | p.1, p.3, p.4 | View filing · Original (NY DPS) |
Page numbers are physical PDF pages.