Part 6 of 11 in the Reforming the Energy Vision series (NY PSC Case 14-M-0101).
By spring 2016, New York had a test for value. What it needed next was information: where the grid was constrained, where load was growing, and where distributed energy resources (DER) could actually defer something. Two filings from March and April show the gap from both ends: one utility's first open solicitation for a growing area, and the Commission's guidance on what every utility's distribution plan had to contain.
Baldwinsville: a load-growth problem put out to the market
On March 11, National Grid filed the request for proposals it had issued in February for "Non-Wires Alternative Solutions" in the Baldwinsville area outside Syracuse. National Grid noted it "has been pursuing Non-Wires Alternative Projects (“NWA’s”) across its service territories since 2011" [F1 p.5].
The need was a growth need. "Loading on the substations serving portions of the Towns of Lysander & Van Buren and all of the Village of Baldwinsville has increased to a level in which the load at risk for a single T&D contingency exceeds the risk threshold accepted in National Grid’s Distribution Planning Criteria" [F1 p.7].
The RFP's structure also tells you how National Grid thought about value. Bidders had to help assess "the load reduction needs by hour of the day, day of the week and months in the year," and the economic test was "an economic analysis that compares the total NWA solution costs against the projected benefits of wires project deferral, reduction in scope or elimination" [F1 p.8]. The final phase would "Discuss warranties of load relief/reward and penalties for not delivering" [F1 p.7]. In other words: a specific constraint, a specific schedule of hours, a comparison against a specific wires project, and consequences for not showing up.
The Distributed System Implementation Plan (DSIP) Guidance Order: information as the core of the model
On April 20, the Commission issued its Order Adopting Distributed System Implementation Plan Guidance. It framed REV's first year as the start of a shift "from the historic model of a unidirectional electric system serving inelastic demand, to a dynamic model of a grid that encompasses both sides of the utility meter and relies increasingly on distributed resources and dynamic load management" [F2 p.4].
The DSIP would be "The vehicle by which improved planning and operations will be defined and implemented." And "At the core of the new model is improved information – improved both in its granularity, temporal and spatial, and in its accessibility to consumers and market participants." The Commission's reasoning was about value and investment: "Greater transparency to market participants, both of system needs and of operational modes that can meet those needs, will encourage innovation and will support efficient private capital investments" [F2 p.5].
What the plans had to show
The order required three filings in 2016: a stakeholder engagement plan due May 5, an Initial DSIP from each utility due June 30, and a joint Supplemental DSIP due November 1 [F2 p.6].
As the order summarizes it, Staff's guidance proposal had the Initial DSIPs address distribution planning in four parts [F2 p.8]:
- "Forecasts of demand and energy growth;"
- "Available resources;"
- "Delivery infrastructure capital investment plans; and,"
- "Beneficial locations for DER deployment."
That list is a load-growth agenda. To find a deferral opportunity like Baldwinsville, you need the growth forecast, the capacity, the capital plan, and the map of where they collide. Until then, a developer outside a utility had no way to know where the value was.
The takeaway
In early 2016, New York's distribution value lived in a handful of places where load had outgrown local capacity, and the information about where those places were sat mostly inside the utilities. The DSIP guidance pointed utilities toward publishing their growth forecasts and their beneficial locations. The June 30 filings were the next test.
Sources
| F# | Filing | Date | Document | Pages cited | Links |
|---|---|---|---|---|---|
| F1 | 14-M-0101, item 725 | 2016-03-11 | National Grid NWA RFP, Baldwinsville | p.5, p.7, p.8 | View filing · Original (NY DPS) |
| F2 | 14-M-0101, item 734 | 2016-04-20 | Order Adopting Distributed System Implementation Plan Guidance | p.4, p.5, p.6, p.8 | View filing · Original (NY DPS) |
Page numbers are physical PDF pages; the DSIP Guidance Order's own page numbers are 3 lower.